Roadmap

Milestone: imagej-2.0-beta1

2 months late (12/09/11 00:00:00)

66%

Number of tickets:
closed:
128
active:
66
Total:
194

First beta release. Class and project design largely set, with focus on bugfixes and completion of primary features. Begin documentation work in earnest, for community review.

Milestone: imagej-2.0-beta2

Due in 5 days (02/10/12 00:00:00)

6%

Number of tickets:
closed:
6
active:
90
Total:
96

Second beta release. Class and project design largely set, with focus on bugfixes and completion of primary features. Begin documentation work in earnest, for community review.

Milestone: imagej-2.0-beta3

Due in 7 weeks (03/23/12 00:00:00)

11%

Number of tickets:
closed:
4
active:
33
Total:
37

Third beta release. Class and project design largely set, with focus on bugfixes and completion of primary features. Begin documentation work in earnest, for community review.

Milestone: imagej-2.0-final

Due in 3 months (05/04/12 00:00:00)

9%

Number of tickets:
closed:
2
active:
21
Total:
23

A 2.0 release of ImageJ, including clear documentation. Focus is on bugfixes and documentation of the infrastructure established earlier (milestone:imagej-2.0-alpha1, milestone:imagej-2.0-alpha2, milestone:imagej-2.0-alpha3, milestone:imagej-2.0-alpha4, milestone:imagej-2.0-alpha5, milestone:imagej-2.0-beta1, milestone:imagej-2.0-beta2, milestone:imagej-2.0-beta3).

Milestone: imagej-2.5

Due in 6 months (08/17/12 00:00:00)

5%

Number of tickets:
closed:
1
active:
20
Total:
21

Intermediate release after 2.0, with new features and bugfixes.

Milestone: imagej-3.0

Due in 11 months (12/23/12 00:00:00)

33%

Number of tickets:
closed:
3
active:
6
Total:
9

Later release for longer term goals and ideas.